Meeting Date: November 4, 2026
Meeting Agenda: https://edmweb.halton.ca/OnBaseAgendaOnline/Meetings/ViewMeeting?id=4639&doctype=1
Operating and Capital Variance Report
Staff project that HCHC will finish 2026 right on its $34.24 million operating budget.
However, this includes $597,050 in unbudgeted one-time revenue, consisting of a $517,000 insurance payout received in 2026 for a 2025 fire and flood at 540 Plains Road East in Burlington. It also includes $80,000 in one-time grant funding (Canada-Ontario Community Housing Initiative and Ontario Priorities Housing Initiative) for repairs at 1150 Dorval Drive in Oakville.
Why does this matter? An unexpected water main break beneath 8 Durham Street in Georgetown in April 2026 caused $1.1 million in damage, leaving HCHC with a $400,000 net cost after insurance deductibles.
Relying on a prior-year insurance payout from a Burlington flood to balance the current budget after a Georgetown water main break is not sustainable fiscal stewardship. It is a warning sign of aging underground infrastructure and rising insurance deductibles.
Furthermore, the 2023–2025 CMHC National Housing Co-Investment Fund program officially ended its three-year funding window on December 31, 2025.
Without renewed funding support from federal and provincial government, HCHC will struggle to maintain or improve current service levels as 8,000+ households sit on the waitlist and shelters operate at 140% capacity.
Capital Works In Progress Review
Across 92 active capital projects, HCHC has $5.9 million (26%) in approved funding sitting completely unspent as of August 31, 2026.
For Milton, this delay is hurting our most vulnerable. Two critical elevator modernization projects in Milton community housing remain severely behind schedule:
- Harmony Court – 111 Ontario St N (Project # H0050A): Approved in 2025 with a $360,000 budget, yet only $5,292 has been spent and $3,867 is in open POs, leaving $350,842 (97.5%) unspent.
- Bruce Apartments – 40 Ontario St S (Project # H0048A): Approved in 2024 with an $80,000 budget, yet only $5,851 has been spent and $5,292 is in open POs, leaving $68,857 (86%) unspent.
Elevators in community housing are essential accessibility infrastructure for seniors and residents with mobility challenges. Approving these projects in 2024/2025 only to leave 86% to 97.5% of the funds unspent late into 2026 is unacceptable.
The Bottomline: We are Falling Behind
In my article on community housing from June 2026, I cited Halton Region’s 2025 Corporate Asset Management Plan, noting that only 53% of HCHC assets are in Good to Very Good condition, highlighting an $8.7 million annual capital funding shortfall just to maintain current service levels.
Right now, HCHC only transfers about $3.8 million into its reserves annually. Even when staff find small surpluses from closing out old projects, HCHC’s baseline contributions remain a fraction of what is required to close that $8.7 million gap.
Our community housing assets are aging faster than we are funding their repairs.